October 02, 2005
Simple Meccano (with a crane!)

This assembly was quite straight forward with every piece coming together perfectly. There didn't seem to be any major adjustments with the actual frame taking only a few days to go up. Securing all the bolts, however, took over a week.
On the next photo you can see the roof covering which was completed last Friday (9/30/2005). As my budget didn't allow for roof tiles I decided to uses metal sheeting, but in four tones. I got the idea from a friend's restaurant "Chez le Ragoût. This is the same place, by the way, where I have all my wine and cheese parties!
